A ravine lot retaining wall in Toronto usually needs approval before anyone digs, even when it’s low: a City ravine permit under Municipal Code Chapter 658, a Toronto and Region Conservation Authority (TRCA) permit, or both, plus a building permit in some cases. The walls that suit these lots are low, free-draining and set back from the edge, on a slope a geotechnical engineer has checked.
For height rules on ordinary lots, read our guide to retaining wall permits in Toronto; for wall systems in general, see Toronto retaining walls.
Two lines decide what you can build
Most ravine lots have two invisible lines across the yard, rarely in the same place.
The City’s ravine line
Chapter 658 covers every tree, fill and grade changes inside the mapped area, including the buffer around the ravine. The line is a free download, or plotted on your survey by the City for a fee.
TRCA’s regulated limit
Under O. Reg. 41/24, a valley with stable slopes runs from the stable top of bank plus 15 m. Where the slope is unstable, the line starts from its predicted long-term position, plus 15 m. TRCA’s address search warns that not every regulated area is mapped.
The stable top of bank is where an engineer expects the valley edge to settle in the long run. It can sit well inside your fence, so flat lawn can be regulated too.
Which approvals does a ravine lot retaining wall in Toronto need?
O. Reg. 41/24 counts site grading and moving material as development, not just building. Its short list of exceptions covers items like an open chain-link fence or a detached patio of 15 m² or less; retaining walls aren’t on it. This is the usual sequence.
| Order | Approval or study | When it applies | Who does it |
|---|---|---|---|
| 1 | Map check and survey with the ravine line and top of bank | Every lot that backs onto a valley | Surveyor; TRCA confirms the top of slope |
| 2 | TRCA pre-application consultation | Regulated land; TRCA must take part if you ask | You or your agent |
| 3 | Geotechnical report and wall design | City grade-change applications; TRCA if requested | Geotechnical and structural engineers |
| 4 | Arborist report | Trees on or next to the lot within 12 m of the work | Arborist |
| 5 | TRCA permit | Wall, grading or fill in the regulated area | TRCA |
| 6 | City ravine permit (Ch. 658) | Trees, fill or grades inside the ravine line | Urban Forestry, Ravine & Natural Feature office |
| 7 | Building permit | Over 1 m, next to public land, an entrance or space the public uses | Toronto Building |
| 8 | Locates, tree fencing, permit posted | Before digging | Contractor |
Top Mark handles the site visit and wall proposal and helps with permits; sealed reports come from the professionals above.
How the City and TRCA rules fit together
The by-law leaves grade changes on TRCA-regulated land to TRCA, but it never hands over the trees. The City’s ravine permit page still lists new and replacement retaining walls, and asks for proof of the TRCA permit where no tree is affected. Ask rnfp@toronto.ca which path your wall takes.
Where the City reviews the grade change, it wants a grading plan, a drainage plan and a geotechnical report covering slope stability. TRCA asks for cross-sections, the setback from the top of slope and erosion fencing, and may add a slope stability assessment; no building permit can be issued until it clears the work. Separately, Toronto’s zoning by-law keeps structures 10 m from a stable top of bank, with exceptions that include ancillary structures on residential lots, so have the City confirm how it treats your wall.
Fines under Chapter 658 run from $500 to $100,000, and up to $10,000 a day while unpermitted fill or grading stays in place. You can also be made to remove the work and restore the slope.
Slope stability: what the engineer is checking
A retaining wall holds back the soil behind it; it doesn’t automatically stop a deeper slide that passes underneath. The geotechnical report looks at the whole slope: soil layers, groundwater, steepness, the creek at the toe, and the weight you plan to add at the top.
TRCA’s guide for ravine and bluff owners recommends a geotechnical engineer for any stabilization or terracing, because a poor installation can overload the crest.
Below Rose Park Crescent, TRCA used buried drainage and a planted rubble buttress. At Canyon Avenue on the West Don, erosion undermined a gabion wall; the replacement is designed in armour stone.
- Trees that lean or curve at the base
- Cracks in the lawn running parallel to the edge
- A fence or patio pulling away
- Seepage part-way down
- Bare soil or gullies below a downspout
- An old wall tipping over the slope
If it’s an existing wall that’s moving, see retaining wall repair in Toronto. Emergency work to stop soil slipping can be exempt from the ravine permit, but only once the City certifies it.
Wall types compared for a ravine slope
| Wall type | Ravine suitability | Why | Watch for |
|---|---|---|---|
| Dry-laid armour stone | Good, if a machine can reach it | Drains through its joints, tolerates movement | Heavy; crest load must be checked |
| Dry-stacked Eramosa in low tiers | Good | Set by hand; small footprint per tier | Modest heights only |
| Hollow pinned precast with geo-grid | Good where height is needed | Hand-carried, gravel-filled, strong | Grid needs a deep cut near roots |
| Small precast block | Fair | Light, economical garden terraces | Rigid; no load above, lower heights |
| Timber | Poor | Stays damp in shade | Rot, then new approvals |
| Poured concrete | Engineer’s call | Deep footing, large excavation | Traps water if undrained |
See finished examples on our natural stone and armour stone walls, large precast block walls and small block walls pages.
Tiered walls or one tall wall?

Two or three low walls mean smaller cuts, less soil behind each and room for roots. But terraces take more of the yard, and an upper wall set close to a lower one loads it, so they’re engineered together. Below the top of bank, the honest answer is often native planting, not a wall. Landscape planning sorts out which parts need structure.
Drainage on a ravine slope
TRCA names excess groundwater and runoff as leading causes of ravine erosion, so drainage has to relieve the wall without feeding the slope.
- Behind the wall: clear stone, filter fabric and socked weeping tile at the base.
- At the outlet: never a bare pipe over the edge. Where water must reach the bottom, TRCA advises releasing it onto large stones; show the outlet on the plan reviewers approve.
- From above: roof water, sprinklers and pool leaks kept off the crest.
- On the surface: a planted strip along the top, and no clippings tipped over the fence, where they smother the roots holding the bank.


Getting materials in without hurting the slope
An excavator tracking along the crest adds load and crushes roots. The City’s minimum tree protection zone in ravines runs from 1.2 m up to 12 m or more for a very large tree, which can close off a side yard. Cutting an access route down the bank can itself start a slide, TRCA warns.
So access often picks the wall. The 60-foot Sandie Dix wall, between two gardens, shows the method: old stone went out and block, gravel and backfill came in by wheelbarrow.


Humber, Don, Highland and Rouge: what changes by valley
Retaining walls in the Humber Valley
Baby Point, Old Mill, Swansea, Weston and Thistletown sit along the Humber. Over 60% of the Lower Humber and Black Creek lands are hard surface, so storms arrive fast. Upstream, see retaining walls in Vaughan.
Don Valley
Rosedale, Moore Park, Leaside and Don Mills back onto the Don and side ravines such as Yellow Creek and Wilket Creek. Near our office, see retaining walls in North York.
Highland Creek
In Scarborough, among the region’s most built-up watersheds. TRCA says heavy rain there sends fast, erosive runoff toward the creek.
Rouge Valley
Rouge, West Rouge and Port Union lots can border Rouge National Urban Park, so confirm who owns the land past your fence.
Cost and timing
Budget the survey, geotechnical report, arborist and permit fees before pricing stone. The City’s fees, new in September 2026 and non-refundable, are $632.51 for grading with no trees, or $262.72 per ravine tree and $549.08 per boundary or neighbour tree for construction, plus replanting deposits. Wall prices are in our Ontario retaining wall cost guide.
TRCA permits normally last two years. Ontario plans to merge its conservation authorities into nine regional bodies from early 2027, so check who takes applications when you file.
Backing onto a ravine?
Book a free consultation and we’ll walk the slope, the access and the permit questions with you. 416.728.2159.
Ravine lot wall questions
Do I need a permit for a ravine lot retaining wall in Toronto?
Almost always. Inside the City’s mapped ravine area, work that changes grades, places fill or affects any tree falls under Municipal Code Chapter 658, and TRCA regulates grading and structures within its limit. There’s no minimum height in either rule. A building permit may apply on top for walls over 1 m near public space. Confirm with the City and TRCA.
Who needs a TRCA permit for a retaining wall?
Anyone building, replacing or regrading for a wall on land TRCA regulates: valleys, flood plains, wetlands and the 15 m allowance past the stable top of bank. O. Reg. 41/24 lists small exceptions, but retaining walls aren’t among them. TRCA can confirm your property’s status in writing through a property inquiry.
What is the top of bank, and how close can I build to it?
It’s the break where tableland meets the valley slope. The stable top of bank is where engineers expect that break to end up over time. There’s no single distance for walls: TRCA reviews the setback case by case, and Toronto zoning keeps many structures 10 m back, with exceptions for ancillary residential structures.
Will a retaining wall stop my ravine slope from eroding?
Only if it’s designed for the actual cause. A wall near the top can’t fix a creek cutting the toe or groundwater seeping mid-slope, and weight at the crest can make things worse. Start with a geotechnical opinion; the answer may be drainage, planting or work lower down.
What wall is best for a ravine lot?
For most back gardens, low tiers of dry-laid natural stone: they drain through the joints, flex slightly and need smaller cuts. Where height is unavoidable, hollow pinned precast with geo-grid can be carried in by hand. Timber is a poor choice on a damp, shaded slope, since replacing it means applying again.
Can I rebuild an old wall on my ravine lot in the same place?
Often, but replacement isn’t exempt: the City lists replacing old retaining walls as permit work, and TRCA asks for a cross-section of any replacement. Expect to be asked whether it can move back, get lower or drain better, and photograph the old wall before anything is touched.
How long should I allow for ravine permits?
Plan in months, not weeks. The survey, geotechnical report, arborist report and consultation come before anything is filed, and TRCA then has 21 days just to confirm the application is complete. Starting in fall or winter gives the best chance of a build next season.