You generally need a retaining wall permit in Toronto when the wall is over 1 m (3′3″) in exposed height and on or beside public property, a building entrance or private property open to the public, and an engineer must design it. A lower wall, or one between private backyards, is usually outside that rule. Ravine, TRCA, tree, boulevard and pool rules can still apply at any height.
This is general information checked against official pages in November 2026, not legal advice. Rules and fees change, so confirm yours with the municipality before you dig.
Retaining wall permit Toronto: quick decision table
| Your wall | Building permit? | Engineer? | Who to ask |
|---|---|---|---|
| Under 1 m, ordinary yard | Generally no; zoning still applies | Generally no | Toronto Building or 311 |
| Over 1 m beside a street, sidewalk, lane or park | Generally yes | Yes | Toronto Building |
| Over 1 m beside an entrance, or a path or driveway leading to one | Generally yes | Yes | Toronto Building |
| Over 1 m, wholly between private backyards | Often no; get it confirmed | Strongly advised | Toronto Building, plus your neighbour |
| Any height, ravine-protected land | Depends on height and location; a ravine permit is separate | Geotechnical report may be required | City ravine office and TRCA |
| Digging near a protected tree | Separate tree permit possible | Arborist | Urban Forestry |
| Any part on the City boulevard | Encroachment rules apply as well | Depends on height | Transportation Services |
| Wall forms part of a pool enclosure | Pool Fence Enclosure Permit too | Depends on height | Municipal Licensing & Standards |
How high can a retaining wall be without a permit in Ontario?
One metre of exposed height is the number to remember, but location matters as much. The Ontario Building Code (O. Reg. 163/24) makes a wall a designated structure when it exceeds 1,000 mm in exposed height beside public property, access to a building, or private property to which the public is admitted. Toronto’s permit list follows the same test and adds that zoning must be met even when no permit is needed.
The grey area is “adjacent”. Other municipalities show how it can be read. The Town of Erin’s guide says the Code doesn’t define it, and treats a 1.8 m wall beside a driveway between two houses as a designated structure, because the driveway is access to the home. Barrie counts anything within a horizontal distance equal to the wall’s height. Toronto may read it differently, so ask.


When a retaining wall needs an engineer
A designated wall falls under Part 4 of the Code, the structural design part, so plan on a professional engineer’s drawings. Below the threshold it is still wise to hire one if the wall carries a driveway, pool or building, stands on a slope, or is terraced closely enough that the tiers act together. Taller engineered walls are often built in large precast block with geo-grid.
Does a 2 foot retaining wall need a footing?
Not a concrete one, in most cases. A 2-foot dry-stacked natural stone or small block wall sits on a compacted ¾″ gravel base with its first course partly buried. A mortared or poured concrete wall is rigid and is a different case: it normally needs a footing below frost, about 1.2 m in Toronto. At 2 feet a building permit is generally not required, though ravine and tree rules still apply.
Guards and pool enclosures on taller walls
Toronto’s Property Standards By-law requires a guard where a wall over 1 m can be reached from the top. Chapter 629 also asks for one where a walking surface sits more than 600 mm above the ground beside it. Posts add load, so they belong in the wall design; on the Kaivan wall, the coping takes the railing.
Around water, the City’s fence rules call for a Pool Fence Enclosure Permit, a minimum 1.2 m enclosure for a single home and nothing climbable outside it. A stepped wall can become that foothold. Where a fence is also a guard, the stricter rule wins.


Property-line walls, neighbours and the boulevard
Start with a survey. If the wall straddles the line, expect to need both owners’ agreement. Toronto’s right-of-entry rules let you step onto a neighbour’s land to repair your own structure when there is no other way: written notice 24 hours ahead, no materials stored there, land restored and damage paid for.
At the front, your lawn may be partly City boulevard. Under Chapter 743, the City charges no encroachment fee for a compliant wall under 0.9 m, while taller ones need encroachment permission.
Ravine by-law, TRCA and tree permits
- Ravine by-law: in protected areas the City’s ravine guidance lists new and replacement retaining walls as permit work and gives no minimum height. New non-refundable fees began September 1, 2026.
- TRCA: in areas regulated by the Toronto and Region Conservation Authority, landscaping and walls may be development activity under O. Reg. 41/24, and the City can’t issue a building permit until TRCA’s permit or clearance is in.
- Trees: injuring a private tree 30 cm or more across needs a permit, and root damage from digging counts. Council has endorsed 20 cm, with a report due in 2027.
The Conservation Authorities Act sets February 1, 2027, or a later prescribed date, for merging authorities, so check who issues permits by then. Our guide to retaining walls on ravine lots goes deeper.
Vaughan, Markham, Richmond Hill and King at a glance
| Municipality | What its documents say | Confirm with |
|---|---|---|
| Vaughan | Under 1 m is on the no-permit list. The grading criteria set walls of 1 m or more back by their height, with engineer certification. | Building Standards, Development Engineering |
| Markham | Under 1 m is on the no-permit list. The infill grading package wants sealed drawings over 0.9 m. | Building Standards, Engineering |
| Richmond Hill | By-law 47-25 can require a site alteration permit for lower walls; its plan lists want a stamped design at 1.0 m or higher. | Building and site alteration staff |
| King | By-law 2021-039 requires an engineer’s design and stamp over 1 m, wherever the wall stands. | Township building and by-law staff |
Thornhill addresses follow Vaughan or Markham, depending on the side of Yonge. These are summaries; ask the municipality which document governs your lot.
Documents checklist for a Toronto application
From the City’s designated structures guide, all as PDFs:
- Application form (the version in force since February 16, 2026)
- Current survey or site plan with the wall, buildings and setbacks
- Zoning summary
- Dimensioned plans, and elevations showing heights
- Sections, connection details and structural calculations
- Schedule 1 designer form (not for engineers or architects)
- Commitment to General Reviews, where the Code calls for it
- Tree Declaration, if trees could be harmed
How to apply, step by step
- Measure and mapRecord exposed height along the wall and what is within that distance: sidewalk, steps, driveway, pool, trees, lot lines.
- Check the overlaysLook up the ravine layer, TRCA’s regulated area search and your survey.
- Ask the City in writingSend a sketch to Toronto Building, and ask which review stream applies and if you need a Zoning Applicable Law Certificate.
- Get the design doneAn engineer draws the wall, drainage, geo-grid and guard.
- Line up other approvalsTRCA, ravine, tree or boulevard approvals come first or run alongside.
- Submit and payA complete package gets a review clock; an incomplete one doesn’t.
- Locate, build, inspect, closeRequest free utility locates, don’t bury work before its inspection, and book the final one to close the permit.
Timelines and fees you can plan around
At 2026 fees, a 20 m wall is $247.40 and anything under about 17 m pays the minimum. The City’s review stream page doesn’t name stand-alone walls, so ask which clock is yours. TRCA’s times start from submission, then from a complete file. Engineering is priced separately; see our retaining wall cost guide.
Toronto adds 50% of the permit fee (minimum $214.79) for work without a permit, stops the job while you apply, and may have it undone. The City says those costs land on the homeowner, whatever a contractor promised.
Want the permit question answered for your wall?
We check height, location and overlays as part of planning. Book a free look at your wall: 416.728.2159.
Replacing an old wall raises the same questions as building new; start with retaining wall repair in Toronto or our retaining walls page.
Retaining wall permit FAQs
Do I need a retaining wall permit in Toronto?
Generally yes, if the wall has more than 1 m (3′3″) of exposed height and is on or next to public property, a building entrance or private property the public can use. Lower walls usually don’t need a building permit, but ravine, TRCA, tree, boulevard and zoning rules may apply. Confirm with Toronto Building.
How high can a retaining wall be without a permit in Ontario?
Up to 1 m of exposed height is the usual Building Code line for walls near public property, building access or property the public enters. Municipal by-laws can be stricter: King requires an engineer’s design over 1 m anywhere, and Markham’s infill grading package asks for sealed drawings over 0.9 m.
Does a retaining wall between two backyards need a permit?
Often not a building permit, because the Code’s list targets walls near the public or a building access. That is not a free pass: grading, ravine, tree and zoning rules can apply, both owners have an interest, and a tall wall still deserves an engineer. Get the City’s answer in writing.
Do I need a permit to replace an existing retaining wall?
Assume the same test applies as for a new wall: exposed height, location and overlays. In ravine-protected areas the City specifically lists replacing old retaining walls as work that needs a permit. Re-gluing a cap or clearing a drain is maintenance and generally doesn’t.
Is exposed height the same as total wall height?
No. Exposed height is the part you can see, from finished grade at the bottom to the top of the wall; buried courses don’t count. Measure at several points, because a wall that is 0.8 m at one end may pass 1 m at the other. Raising the grade or lowering a driveway changes the figure.
How long does a Toronto retaining wall permit take?
Complete House Stream applications are reviewed in 10 business days, though the City doesn’t say which stream a stand-alone wall uses. Engineering comes first, and TRCA can take 21 days to check completeness plus 30 or 90 days to decide. Starting in winter for a spring build is sensible.
Do I need a guard or railing on top of my retaining wall?
In Toronto, a wall over 1 m that people can reach from the top must have a guard on its open sides, and walking surfaces more than 600 mm above the ground beside them generally need one too. A pool enclosure has its own height and climbing rules, and the stricter standard applies.
Who applies for the permit, me or the contractor?
Either can, but the owner is responsible. Toronto accepts applications signed by the owner or an authorized agent. Top Mark can help you through the process while the wall is being planned; the engineer supplies the sealed drawings and any general review commitment.